| March 3, 2017 | This project is now complete. |
| December 16, 2016 | A final change order will be presented to the Board for consideration at the 12/19/2016 Board Meeting. |
| November 25, 2016 | All work is complete. Staff is working to closeout the project. |
| November 18, 2016 | Restoration efforts continue. |
| November 11, 2016 | All installation work is complete and restoration efforts are underway. |
| November 4, 2016 | The copper for grounding grid has been installed and welding of the various pieces has begun. |
| October 28, 2016 | Excavation for the installation of the grounding system have begun. |
| October 21, 2016 | Misfits Construction was in laying out the project. Construction activities should begin next week. |
| September 30, 2016 | A pre-construction meeting was held this week. Construction is anticipated to begin in the middle of October. |
| September 16, 2016 | A contract was awarded at the Board Meeting on 09/12/2016. A pre-construction meeting is scheduled for 09/27/2016. |
| September 2, 2016 | Staff is working to prepare a recommendation for the Board at the 09/12/2016 board meeting. |
| August 26, 2016 | A bid opening was held on 08/23/2016. Staff is working to confirm the contractor is qualified to perform the work. |
| August 5, 2016 | This project will be advertised on 08/05/2016. The bid opening will be held on Tuesday, August 23, 2016 at 10:00 AM at the Public Works Department, 11 West Home Avenue, Villa Park, IL. |